One of the country’s largest infrastructure and energy projects is getting underway in the Croatian region of Lika: The state-owned energy utility Hrvatska elektroprivreda has issued a call for bids for the main construction work on the Kosinj hydroelectric power plant system. With an estimated net investment of 480 million euros, a massive reservoir and a new hydroelectric power plant are being built in the municipality of Perušić, which will significantly expand energy production in the karst region while permanently altering the landscape of the Kosinj Valley.
History and Project Objectives
The plans date back to the 1980s, when the first concepts for expanding the Senj hydropower system—which has been in operation since 1966—were developed. There, water from the Lika and Gacka rivers is already being used to generate electricity. After a long hiatus, preparations resumed over the past decade and led to the granting of a site permit in 2019. The project serves a dual purpose: on the one hand, it aims to harness the remaining hydroelectric potential of the Lika River and optimize the existing Senj system; on the other hand, the reservoir will provide flood protection in a valley that is regularly affected by severe flooding in the winter and spring.
A new reservoir
Downstream from the existing Kruščica Lake and the Sklope hydroelectric power plant, the new Kosinj reservoir will cover an area of 11.45 square kilometers and hold approximately 340 million cubic meters of water. For the sparsely populated region around the villages of Gornji Kosinj and Mlakva, the flooding will have a profound impact. A county road, a local road, and nine local transformer stations will be permanently submerged, thereby also cutting off the existing power connection to the village of Bakovac.
The utility company is therefore required to relocate residents from the future flood zone and to build a new power grid, including a substation, for Bakovac. Regardless of the current main tender, extensive preparatory work is already underway on site: A replacement road from the Kosinj Bridge to Bakovac is under construction, the connection from Studenci to the Sklope power plant is being renovated, and a new tunnel will divert the Bakovac stream directly into the Lika River in the future.
Engineering in the Karst
The reservoir will be enclosed by earth-filled dams with clay cores, which are adapted to the geological characteristics of the Lika Karst:
- Kosinj Dam: The main structure is approximately 58.5 meters high and 400 meters long, and serves as the site for the new power plant.
- Bakovac Dam: This second major barrier is 55 meters high and extends over a length of 450 meters.
- Sedlo Dam: As the third barrier, this dam closes off the reservoir with a height of 22.4 meters.
- Ground Sealing: To minimize water loss in the porous subsoil, a cement mixture is injected into the ground through boreholes up to 100 meters deep over a length of 5.6 kilometers.
- Turbine Technology: The new power plant at the Kosinj Dam will be equipped with two turbines rated at 22 and 12.6 megawatts, respectively, which are designed to operate flexibly at both full and lower water levels.
Modernization and Timeline
In parallel with the new construction, the existing Sklope hydroelectric power plant will also undergo extensive retrofitting and be adapted to the new reservoir. Since the powerhouse is located about five meters above the future maximum water level, the plant will be equipped with a new spillway on the dam as well as a modernized turbine that will increase its capacity from 22.5 to a maximum of 24.7 megawatts.
The contract is set to run for 75 months, with the construction phase alone lasting six years. After an initial year of preparatory work, four years will be devoted to dam and power plant construction as well as ground grouting, while the final year is reserved for the initial filling of the reservoir and trial operations. The weather poses a particular logistical challenge, as the sensitive clay for the dam cores can only be installed between April and October.
Award and Outlook
The bidding process will take place as a two-stage negotiation procedure, during which interested construction companies may submit their applications to participate by March 1, 2027. Qualified bidders will then receive detailed technical specifications and the scope of work and will enter into negotiations following the submission of initial bids. In the final award decision, price will be the primary criterion, accounting for 90 points, while an additional 10 points will be awarded based on a warranty period of between two and five years; a bank guarantee of 14.4 million euros is also required. The Kosinj project in the Lika region will create one of the most technically sophisticated hydraulic structures in Southeast Europe, designed to secure Croatia’s hydroelectric power production in the long term.