News for Skippers: The completion date for the new breakwater at Prvić Luka has been set.

best charter yacht in croatia

For many skippers in the Šibenik archipelago, the sheltered bay of Prvić Luka is one of the most beautiful stops of all. There’s now an important update regarding the ongoing renovation of the breakwater: Although construction is taking a little longer than originally planned, the news for the upcoming boating season is entirely positive.

Photo: Port Authority of the Šibenik-Knin County / ŽLU ŠKŽ

More Substance Instead of a Rush Job

According to the Šibenik-Knin County Port Authority (ŽLU ŠKŽ), the work is now scheduled to be completed by February 25, 2027, at the latest, instead of December 6, 2026—an extension of 81 days. The reason for this is easy for seafarers to understand: It wasn’t until the renovation began that it became clear that the old structure of the breakwater was in much worse condition than expected.

Instead of making temporary repairs to conceal the damage, extensive additional work—including new shipments of natural stone from Pazin—was approved. As a result, the total cost will rise by approximately 316,000 euros to 3.02 million euros, covered by additional funding from the Ministry of the Sea and the county. For us boaters, this means one thing above all: a pier that is solid from the ground up, where we can once again spend the night in comfort even when the sea is rough.

Photo: Port Authority of the Šibenik-Knin County / ŽLU ŠKŽ
Sailor Croatia App

Back in time for the first cruises

While construction will continue during the winter months—with regular passenger service to the island continuing uninterrupted—the construction site will be completed by the end of February. When the first yachts and motorboats set sail from Šibenik, Vodice, Tribunj, or Biograd in the spring of 2027, we’ll once again be able to moor directly at the newly redesigned pier.

No sooner have the moorings been taken than you’re greeted once again by exactly what makes Prvić Luka so special: car-free cobblestone streets, the Faust Vrančić Memorial Center just around the corner, an evening stroll over to Šepurine, and a sundowner at one of the little konobas right on the water.

Key facts at a glance:

  • Completion: No later than February 25, 2027 (81-day extension)
  • Investment: Approximately 3.02 million euros (an increase of about 316,000 euros)
  • Current operations: Regular service and passenger transport via Šepurine will continue uninterrupted until the opening