It was supposed to be the big winter comeback of the year: After nine years in exile at the Višnjik Sports Center, the Advent ice rink was finally set to return to the Old Town peninsula—right next to the historic Forum, complete with an additional skating lane and the blessing of the historic preservationists. Advent kicked off in Zadar on November 24. The only thing missing from the Forum? The ice.
Mayor Šime Erlić has now had to give the final nod: No one will be skating at the Forum this year. However, this isn’t due to the mild Dalmatian climate, but rather to a homegrown contracting debacle that’s melting faster than any ice in the south wind.
Started too late, planned too hastily
Anyone who wants to set up a prestigious project costing 200,000 euros net in time for the start of Advent on November 24 should keep an eye on the calendar. However, the city of Zadar didn’t issue the contract for the rental, setup, and operation of the mobile ice rink until September 10. Two bidders entered the race: the Zagreb-based company Wonderland Factory with a bid of 215,437.50 euros and its competitor Arctic from Rijeka with a bid of 250,000 euros.
On October 23, the city awarded the contract to the lower-priced bidder from Zagreb—whereupon Arctic filed a complaint with the State Public Procurement Review Commission (DKOM) on November 2. Suddenly, things got hectic at City Hall. The city pleaded with the commission to allow the contract to proceed despite the pending complaint, arguing that the public interest was paramount and that otherwise the launch on November 24 would be impossible. The response from Zagreb was as terse as it was damning: Anyone who doesn’t issue a call for bids until September must expect objections. Time pressure resulting from one’s own sloppy planning simply cannot override public procurement law.
Failed due to cooling technology—and an untranslated certificate
The procurement commission’s ruling becomes particularly bitter when one looks at the reasoning behind it. After all, Arctic didn’t simply file an objection out of spite—the city had handed the competition a golden opportunity on a silver platter:
- Questionable cooling technology: The city did not properly review the technical specifications for the winning bidder’s cooling system. Documents submitted later by a British company (London Climate Hire) left completely unclear what role the company actually plays and whether the technical modifications are guaranteed both legally and in practice.
- The Missing Translation: The certification for the prospective skating school instructor was not available in Croatian—even though the city had explicitly required exactly that in its own request for proposals.
The result: The DKOM overturned the award decision in its entirety, sent the case back to Zadar, and ordered the city to pay an additional 1,476.25 euros in procedural costs. And because a proper re-evaluation under public procurement law can take months, the schedule for this season is completely falling apart.
Free Ferris wheel—yay; ice rink—yuck
The irony of the story lies just a few minutes’ walk away. For the Advent Ferris wheel—which features no fewer than 21 enclosed, heated gondolas that Split must do without this year—Erlić cleverly enlisted the tourism board and secured the attraction at no cost to the city budget. In its own flagship call for proposals for the Forum, however, the city administration tripped over its own rules.
The opposition, of course, isn’t going to let this opportunity slip by. Erol Gaši, head of the SDP in Zadar, is demanding an investigation into who is responsible and hits the nail on the head: Advent should not be a matter of improvisation on the part of the city administration.
But that’s exactly what’s happening now. The city, the tourism board, and local restaurant owners are scrambling to put together an alternative program for children and families at the Forum. For a city that likes to play in the big leagues of Croatian tourism, this is a painful lesson: On the Adriatic, you don’t need above-freezing temperatures to ruin an ice rink—a late start, lax oversight, and a forgotten translation are more than enough.